Ocean Spray

OCEAN SPRAY

Overview

  • When global demand for Ocean Spray dried cranberries doubled within three years and was projected to double once again, the company made its largest capital investment in a manufacturing facility to date with a 130,000 SF expansion that doubled the plant’s size to 440,000 SF. The plant produces both sweetened dried cranberries and cranberry juice concentrates.

Project Highlights

  • The facility incorporated some of the latest technologies in energy and environmental efficiency, including a wastewater  treatment facility, energy-efficient lighting, and an expansion of a system that converts methane from the Veolia Cranberry Creek Landfill into clean energy to power the plant.
  • A new fully-racked warehouse for both ingredients and finished goods increased storage capacity. The expansion enabled the plant to produce more than 30 million pounds of sweetened dried cranberries per year.
  • Major accomplishments of the project included design and implementation of 5S standards in creating state-of-the-art maintenance shop and quality control lab spaces.

 

The J.M. Smucker Company

THE J.M. SMUCKER COMPANY

LEED New Construction v3 Certified

Overview

  • In order to ensure long-term competitiveness and meet growing demand, The J.M. Smucker Company decided to build a 300,000 SF facility that embraced the latest equipment and technologies on its corporate campus.

Project Highlights

  • This new space, which was located adjacent to an existing finished goods warehouse on their 35-acre corporate campus featured rail receiving, bulk dry and liquid commodities, three high-speed production lines and five portion control lines.
  • Dennis Group adopted a phased construction approach in order to seamlessly transition operations from an existing facility.
  • Careful planning and permitting were required since the site had several wetland areas. In addition to mitigating the wetland disturbance, sustainability was a key focus of the project since the company has committed to be environmentally conscious and socially responsible.
 
 
USGBC ® and the related logo are trademarks owned by the U.S. Green Building Council and are used with permission.

MOM Brands

MOM BRANDS

Overview

  • Following the launch of Malt-O-Meal;s Better Oats® line of instant oatmeal products, the company undertook a two-phase $136 million expansion of its Asheboro production facility.

Project Highlights

  • Dennis Group provided complete design-build services for an expansion to Malt-O-Meal’s Asheboro facility which included development of a 35 acre site, including a new rail siding for unloading bulk grains, a rail receiving building and a 550,000 sq ft. two level building addition constructed of pre-cast and cast in place concrete as well as structural steel.
  • The site also includes a retaining wall approximately 20’H by 500’ to make up for the elevation difference between the rail siding and remainder of the site.
  • The expansion also included the construction of a 80,000 sq ft. warehouse for storing packaging materials and finished product.
  • This project included the addition of utility infrastructure (chillers, air compressors and hot water system), eleven bulk commodity bins, and two bulk liquid storage tanks. The process additions included the installation of three complete cereal production lines with fully automated final packaging.

 

Sabra

SABRA DIPPING COMPANY

LEED New Construction v3 Gold
LEED New Construction v3 Silver
LEED New Construction v2.2 Silver

Overview

  • To meet rapid growth in the hummus and chilled dips sector, Sabra enlisted Dennis Group to provide full design-build services for the world’s largest hummus facility.

Project Highlights

     Named “Food Plant of the Year” by Refrigerated & Frozen Foods magazine

  • The initial facility was 120,000 SF which included a 40,000 SF finished goods distribution center – a 100,000 SF expansion was added later in less than 14 months from concept to commissioning.
  • Dennis Group took a highly manual operation in Sabra’s former location in Astoria, New York and transformed it into a fully-automated operation giving Sabra a more than 200 percent capacity increase.
  • A custom integrated CIP system ensures the product is never exposed to the manufacturing environment and that the finished product is not handled until it has been hermetically sealed.
  • The project attained LEED Gold and LEED Silver Certifications for energy savings, environmental impact and sustainability.
    • A massive water collection system allows for the reuse of 500,000 gallons of rain and process water each year
    • Low VOC levels were specified for all paints, coatings, sealants, adhesives, and carpet systems
    • Composite wood products are free of urea-formaldehyde
    • Outdoor air ventilation far surpassed the recommended guidelines of ASHRAE

 

 
USGBC ® and the related logo are trademarks owned by the U.S. Green Building Council and are used with permission.